A one-page updated project timeline for the Woody Creek development (author: Pete Schnepp) that lists target milestone dates and phases: loan closing (early August 2025); permit approvals and contractor mobilization (Aug 2025); renovation start (Sept 2025) and lease-up completion (Mar 2026); stabilized operations (Apr 2026–Jul 2031); and potential broker marketing and sale window (Jan 2031–Jul 2031). The purpose is to provide investors an up-to-date schedule through stabilization and possible sale.
Questions this document answers
Early August 2025.
August 2025.
Renovation start: September 2025; Lease-up completion: March 2026.
April 2026 to July 2031.
January 2031 to July 2031.